    User name adaq

    Log entry time 08:04:13 on February 9, 2009

    Entry number 259979

    keyword=Beam Time Accounting
    Hall A

    02/09/09 0000-0800
    Experiment #: E06-014
    Shift Leader: Yoomin Oh
    Shift Workers: Al Tobias , Navaphon Muangma

    00000100020003000400050006000700Total Time
    Acceptable Beam
    in Use
    0.180.150.090.030.470.640.160.522.24
    Beam Available
    but Not in Use
    0.800.630.810.910.510.310.370.344.68
    Beam Not Available
    or Unacceptable
    0.030.220.100.050.020.050.470.131.07
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.001.001.001.000.420.750.920.927.00
    Planned Config-
    uration Change
    0.000.000.000.000.500.250.080.080.92
    Unplanned
    Experiment Down
    0.000.000.000.000.080.000.000.000.08
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00
    Bbite0.000.000.000.000.080.000.000.000.08

    Comments: 00:00-04:00 waiting for adjusting raster size 06:10-06:50 MCC beam tuning

    Data Entry by: Yoomin