Main INDEX
Monthly INDEX
PREV
NEXT
Make New Entry,
Make Followup Entry
User name R. Michaels
Log entry time 14:40:03 on April 1,2009
Entry number 266593
keyword=R-HRS scalers and other to-do
R-HRS scaler basic readout finished and tested with xscaler.
I modified the TS readout to be like L-HRS and bigbite in terms
of reading normalization scalers for every event and for synch
events, etc. But ... I don't have a TIR on the R-HRS TS, so I
need to hunt for one and try it out.
Here is a to-do list. If there's some confusion about who is
doing what, ask whoever has the overview (spokesperson ?).
Task ....... who (I think)
1. Obtain TIR for R-HRS TS .... Bob
2. Gating of R-HRS scalers by target, helicity, run .... Bo Z.
3. Check gating elsewhere (I think cabling was undone) ... Bo Z.
4. Target & helicity state into R-HRS datastream ... Bo Z./Joe
5. Revive HAPPEX DAQ and Lumi insertions .... Bob/Joe
6. Connect HAND to R-HRS ..... Bryan/Bob
7. Restore L-HRS DAQ .... Bob/Vince