Main INDEX
Monthly INDEX
PREV
NEXT
Make New Entry,
Make Followup Entry
User name jpchen
Log entry time 09:13:42 on May11,2009
Entry number 272526
keyword=planed hall activities
Planed activities in the hall:
1) Target cell switch (Joe/Yi')
2) Target ladder survey (alignment group)
3) Right VDC_b HV (Bogdan/Albert)
4) Right scintillator PMTs (left side, S1: 1, 4, 6, S2:1,2,3,4) (Bogdan/Albert)
5) Move BB (Ed and company)
6) ND timing and BB DAQ (Bryan)
7) ROC8 busy signal issue?
Later
1) ~7 pm, hall will be locked for laser alignment.
2) Afterwards, target tests/spin-up.