    May 17, 2009
    SL: V. Sulkosky
    TO: D. Parno
    3rd: W. Luo

    Owl Shift Summary:
    +++++++++++++++++++++++++++++++++++++++++
    00:00 Begin shift with no beam.
    02:55 Move to target to empty position.
    03:10 Beam back, begin beam checkout procedure.
    03:10 Turned off HAND HVs for beam tuning.
    03:32 Beam profile looks good from Harp scans:
              A: 111 x 162 microns
              B: 151 x 171 microns
    03:34 Move to Optics target to check raster.
    03:41 Move to polarized 3He target and ask for 3x2 raster size.
    03:48 Ask for 6 x 6 raster size (10 x 8 MCC units).
    03:53 Ask for 4 x 4 raster size (7 x 5 MCC units).
    03:57 Resume Production on 3He at 10 uA.
    04:05 Restored HAND HVs.
    04:07 First production runs with HAND on.
    05:43 Change left HRS momentum setting to 2.277 GeV/c.
    06:43 Noticed that left HRS stopped counting at 1.5 M events during run 2347.
    07:16 Restart happex, new run number is 31385.
    07:45 NMR measurement: 63.0%

    Left Run Summary:
    Start    Run       Events          Comments
    ===============================================================================
    23:35   2337       207 k           No beam, cosmics
    02:49   2338       842 k           Cosmics, beam near the end
    03:37   2339       335 k           Raster Check on BeO (4 x 4)
    03:46   2340      88.5 k           Raster Check on 3He (2 x 2)
    03:51   2341        82 k           Raster Check on 3He (6 x 6)
    03:58   2342       1.4 M           Production on 3He
    04:08   2343       5.0 M           Production on 3He
    04:39   2344       5.0 M           Production on 3He
    05:11   2345       5.0 M           Production on 3He
    05:54   2346       5.0 M           Production on 3He, P0 = 2.277 GeV/c
    06:21   2347       1.5 M           Production on 3He, CODA Stopped counting
    06:47   2348       5.0 M           Production on 3He
    07:16   2349       5.0 M           Production on 3He
    07:46   2350       ?? M            Production on 3He, continued into Day
    shift
    
    
    
    Right Run Summary:
    Start    Run       Events          Comments
    ===============================================================================
    23:34   21243      293 k           No beam, cosmics
    02:48   21244      954 k           Cosmics, beam near the end
    03:50   21245       75 k           Raster Check on 3He (6 x 6)
    03:57   21246     1.27 M           Production on 3He,  HAND HV's off 
    04:07   21247     4.52 M           Production on 3He,  HAND HV's on 
    04:39   21248     4.52 M           Production on 3He
    05:11   21249     4.53 M           Production on 3He
    05:53   21250     4.1  M           Production on 3He, P0 = 2.277 GeV/c
    06:21   21251     3.7  M           Production on 3He, P0 = 2.277 GeV/c
    06:46   21252     4.09 M           Production on 3He, P0 = 2.277 GeV/c
    07:16   21253     4.09 M           Production on 3He
    07:45   21254      ?? M            Production on 3He, continued into Day
    shift