    User name adaq

    Log entry time 16:02:46 on May 18, 2009

    Entry number 274536

    keyword=Beam Time Accounting
    Hall A

    05/18/09 0800-1600
    Experiment #: E05-015
    Shift Leader: J.P. Chen
    Shift Workers: B. Anderson , B. Michaels

    08000900100011001200130014001500Total Time
    Acceptable Beam
    in Use
    0.580.690.800.860.760.840.860.876.25
    Beam Available
    but Not in Use
    0.270.040.150.020.170.050.050.040.80
    Beam Not Available
    or Unacceptable
    0.140.280.050.130.070.100.080.090.94
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    0.731.000.851.000.831.001.001.007.42
    Planned Config-
    uration Change
    0.270.000.150.000.170.000.000.000.58
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00
    Bbite0.000.000.000.000.000.000.000.000.00

    Comments: 8:00- 16:00 production data taking configuration changes are target movements, reference cell filling/evacuations and NMRs.

    Data Entry by: jpchen