keyword=LabView restart
At the end of the OWL shift the LabView started acting funny. The NMR
freq. sweep program seemed to be working - the status light was blinking
but the temperatures were not updating. On the other hand, EPICS daemon
froze - status light was not blinking and I also was not able to kill it.
We have waited until the current production run ended, than killed
the LabView and restarted it again. We stared the EPICS daemon and
the NMR frequency sweep. After the restart we did another NMR
measurement. The polarization at the moment is 54.4%
A copy of this log entry has been emailed to: yqiang