    05/27/09 0800-1600
    Experiment #: E05-102
    Shift Leader: William Tireman
    Shift Workers: Brad Schoenrock (3rd), Todd Averet (Target)

    08000900100011001200130014001500Total Time
    Acceptable Beam
    in Use
    0.820.710.750.780.690.970.700.876.28
    Beam Available
    but Not in Use
    0.030.140.190.110.180.030.300.131.11
    Beam Not Available
    or Unacceptable
    0.150.150.060.110.130.000.000.000.61
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.000.870.820.920.820.000.701.006.12
    Planned Config-
    uration Change
    0.000.130.120.080.181.000.300.001.82
    Unplanned
    Experiment Down
    0.000.000.070.000.000.000.000.000.07
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.070.000.000.000.000.000.07
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00
    Bbite0.000.000.000.000.000.000.000.000.00

    Comments: Started shift from Owl with 12 uA beam on target. Polarization check at 0805 hrs: 57.9% Switched to H2 reference cell at 0928 hrs Switched to N2 gas in reference cell at 1014 hrs Switched back to He-3 polarization at 1120 hrs. Beam back by 1125 hrs. 11 uA beam request per Doug H. request Moeller measurement in progress. Started at 1249 hrs.

    Data Entry by: William Tireman