    Log entry time 08:03:58 on May 29, 2009

    Entry number 277278

    keyword=Beam Time Accounting
    Hall A

    05/29/09 0000-0800
    Experiment #: E05-102
    Shift Leader: Eric Jensen
    Shift Workers: TO - Matthew Posik, 3rd - Eli Piasetzky

    00000100020003000400050006000700Total Time
    Acceptable Beam
    in Use
    0.780.770.910.930.200.660.820.125.18
    Beam Available
    but Not in Use
    0.030.060.040.040.770.320.070.692.03
    Beam Not Available
    or Unacceptable
    0.190.160.050.030.030.030.100.190.79
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    0.970.930.970.950.230.680.000.004.73
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.000.00
    Unplanned
    Experiment Down
    0.030.070.030.050.770.321.001.003.27
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.030.070.030.050.000.000.000.000.18
    Other0.000.000.000.000.770.321.001.003.08
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00
    Bbite0.000.000.000.000.000.000.000.000.00

    Comments: 46 minute down time due to Q1 cryo problems for both HRS

    Data Entry by: Eric Jensen