0800 Production running, transverse target
0855 NMR=58.2%, BHWP is now OUT, New Compton run started, new HAPPEX run started=31506
0900 Start production runs, 3438, 22309
1025 Runs 3438, 3439, 22309, 22310 have the BHWP status incorrectly listed as IN and the target polarization incorrectly listed as 56.7%.
1140 Target NMR=58.3%, Yi will rotate target field to longitudinal, positive, move to N2 reference cell, pressure=18 psig.
12:10 Move back to pol3he target position. Orientation is longitudinal, positive. NMR measurement=55.8%
1325 MCC informs us that the cooling water to the beam dump is tripped off. No Beam until fixed. End HAPPEX and Com[pton runs too.
14:02 Resume production running