    keyword=Planned Configuration Changes

    During the down, the Hall A Neutron Detector (HAND) will be moved back to 8 meters from target and 54 degrees. [There are marks on the floor where this is.] The sieve plates for the two spectrometers should be installed.

    The right arm momentum should be set back to 2175 MeV/c and the quads. cycled.

    We should also reinstall the Hydrogen (replacing Deuterium) in the reference cell.