17:30 Crew chief informs us that we will have tune beam in the next 10 minutes
18:40 Crew chief called us back and said beam is now definitely imminent; they had some unexpected problems over the past hour.
18:55 They are sending tune beam down our hall
20:00 MCC says we have beam to our dump. We requested 5 microamps
20:25 The beam has been positioned well and we have requested harp scans. They have turned on energy and position fast feedback
21:00 3A and 3B harps scans are done; requested 7-18 Harp scans
21:20 Repositioning beam after quads were retuned to make spot bigger
21:40 Beam has been set up as planned, but the DAQ is highly unstable and Bob recommends that we take an access to fix it.
23:10 Bob informs us that controlled access work has been completed. A cpu was swapped out.
23:30 We have asked MCC to put us back in Beam Permit and restore 5
microamps. They informed us that we have to wait until they have
completed Hall C tuning.