User name dalton
Log entry time 18:49:57 on August 25, 2009
Entry number 285971
keyword=Hall status
We have closed up that hall.
MCC says that we can have beam in 1 hour.
John Musson has completed his work in the hall and would like to
calibrate the BPMs when we get beam.
Following this calibration we will let the operators calibrate the ion
chambers for high current running.
Thus, the PREX tests are unlikely to start before 10 pm.