    We have closed up that hall.

    MCC says that we can have beam in 1 hour.

    John Musson has completed his work in the hall and would like to
    calibrate the BPMs when we get beam.

    Following this calibration we will let the operators calibrate the ion
    chambers for high current running.

    Thus, the PREX tests are unlikely to start before 10 pm.