Log entry time 16:01:08 on October 4,2009
Entry number 293114
keyword=Day shift summary
Shift workers:
Ole Hansen (SL)
Guiseppe Russo (TO)
Brian Quinn (3rd)
08:00 Start shift with production data taking in progress.
08:45 Start beam tuning for Moller measurement. End production data taking. Taking pedestals in parallel to Moller.
14:30 Moller measurement ends. It took unusually long because many additional tests were done. See separate log entries.
14:50 Beam recovery after Moller done. Resuming production data taking.
16:00 End shift with data taking in progress.
Run summary
-----------
12933 44.9k good pairs
12934-12943 pedestal runs
12944 in progress at end of shift