    keyword=Day Shift Summary

    8:00 Shift starts with beam starting to return. Ask for them to correct the BPMA Y.

    8:25 MCC fixed BPMA Y.

    8:27 Start production at 100uA.

    8:40 LUMI widths 1400 reduce current to 96uA to check.

    10:32 MCC starts injector work. No beam.

    16:00 Shift Ends no Beam


    Production Runs
    13280 8:26-9:22 100k
    13281 9:22-10:11 86k
    13283 10:17-10:33 26k