    User name Armstrong

    Log entry time 22:42:51 on October 24, 2009

    Entry number 296504

    Followups:

    keyword=Left Q2 trips, but at higher current

    OK, we made some improvement - we got up to 1125 A before Left Q2 trips, with the new lead flows. This is a big improvement, since we had before had it tripping at 668 A, so we have almost doubled the current by increasing the lead flows from 95-100 l/m to 110l/m.

    So, this gives us some hope, but we decide not to go any further, but to establish beam on the Loop 1 target...