User name miham
Log entry time 17:21:56 on December 4,2009
Entry number 304662
keyword=Beam problems and Controlled Access
We called MCC and they need to make an access to Linac to
fix the valve. At the moment they are waiting for the
Vacuum crue. They are hoping to fix the problem within an hour.
There is also a problem with a left arm (the rate in this
spectrometer is to low). Therefore we requested for a escorted
controlled access to fix the problem. At this time MCC
(because of their own problems) can not send ARM to sweep
the hall A. They told us to wait until they are done
sweeping the Linac tunnel.