16:00 Status at start of shift:
Moller spin dance in progress...Sasha, Roman, et al. in charge...
I decide to allow the TO and the 3rd to depart, leaving contact numbers, as I am a trained TO, and the expectation is that Moller data-taking will continue much of the shift. I'll be here to answer the phone, monitor the target, and deal with the BTA...
21:03 Moller spin dance completed.
Results of spin dance are posted here: halog 316534
22:30 MCC calls: Matt has completed Mott measurement, beam is now transverse vertical.
23:16 Start Pb target beam startup/recovery procedure; ask for 5 µA beam on empty target, with raster on
23:25 MCC gets to correct nominal beam positions: BMA4A = -0.4, +0.9 and BPM4B = 0, +2.1
23:40 Spot++: looks good. Go to BeO viewer.
00:17 Go to Pb target #3; run Spot++.
Thanks to Sarah Phillips for help on the tail end of the shift...
00:25 Shift ends, hand off to the next crew....