    Log entry time 08:05:39 on April 29, 2010

    Entry number 320157

    keyword=Beam Time Accounting
    Hall A

    04/29/10 0000-0800
    Experiment #: E06-002
    Shift Leader: V. Sulkosky
    Shift Workers: X. Deng, D. Wang

    00000100020003000400050006000700Total Time
    Acceptable Beam
    in Use
    0.000.000.000.330.971.001.000.924.22
    Beam Available
    but Not in Use
    0.000.000.000.220.000.000.000.050.27
    Beam Not Available
    or Unacceptable
    1.001.001.000.450.030.000.000.033.52
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.001.001.000.781.001.001.000.957.73
    Planned Config-
    uration Change
    0.000.000.000.220.000.000.000.050.27
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments: 00:00 Start of shift no beam due to FBB problem. Thanks for the great beam MCC!

    Data Entry by: V. Sulkosky