User name jmammei
Log entry time 16:51:32 on June 17, 2010
Entry number 327092
keyword=Run Coordinator Daily Summary, June 16 Swing - June 17 Day
Summary for June 16 Swing - June 17 Day
General Summary
- Beam not returned until owl shift, after all the testing and
surveys
- Production running (single arm) beginning on owl shift
- Right dipole repairs
- Warmed up the target to get rid of the N2 ice
24 Hour Beam Time Summary (Starting Tuesday Swing)
- ABU: 3.88
- BANU: 6.41
- BNA: 13.71
Accumulated Charge Summary
- Last 24 hours: 0.13 C (single-arm, corrected)
- Total: 43.3 C (single-arm, corrected)
Main Events/Issues:
- Target warm-up worked! (see log entry )
Right dipole working as of now
70uA test planned for 6pm on empty target
Try to establish 70uA on PbD#1 during owl shift
Plans for the next few days: