I got a call from Philip who agreed of the plan for the next few hours : we are finishing up the last run of optics and will do the E/2 run shortly.
I arranged with the techs to come in for the polarity change and with MCC to have the pass change happening at 1PM. Thanks to them for accommodating the plan change.
As soon as the E/2 runs are finished we will call for controlled access and have a full survey so that Albert can work on the replacing the gas cerenkov tubes.
We should be ready to complete the last tests of phase I when beam comes back.