    User name Markowitz

    Log entry time 18:56:52 on July 02, 2010

    Entry number 329478

    keyword=First beam for permanent magnet/ corrector coil commissioning

    We currently have pulsed beam and the septum is set at 480 A (0.7 GeV/c). However the MCC has determined that the FSD interlock on the septum current is not properly reading back. The current is reading back, but not the FSD. MCC has called in the PSS on call.