Log entry time 14:47:28 on July 3,2010
Entry number 329662
keyword=Flashing light
14:40 Radcon says to leave the portable light in the septum. It has been there for weeks. Ed Folts was also called but has not returned our message yet. We are now back in beam permit and septum current is back up. MCC is continuing set up for max allowed current using ion gauge as vacuum limit. Waiting for beam.