All magnet power supplies are now operational, but the left arm NMR
multiplexer is not working, so we are not able to lock the dipole. We
will replace the multiplexer with a spare from Hall C tomorrow, but we
are also working on allowing the Hall probe to regulate the dipole as a
backup. In an effort to not heat up the target, which is no longer in
liquid phase due to the Qweak target cooldown, we will not take beam
tonight.
Because of a bad valve in the south linac today, Hall B lost beamtime
which pushes their calorimeter calibration back several hours. This
moves putting all three halls online to Monday. The Compton tune will
occur sometime in the week after that.
Plans for the next 24 hours:
Plans for the next week: