User name Jin Huang
Log entry time 23:57:09 on October 11, 2010
Entry number 334459
keyword=Shift Summary : Oct 11 Swing
Crew
- SL: Jin Huang
- TO: Bo Zhao
- Analysis: Salvatore Frullani
Time Line
- 1600 Shift started. Status:
Controlled Access
HRSL: 27.5 degree, 3.194GeV (Elastic +3%)
Empty target, cryo status stable
MCC estimate beam delivery around 7PM, shift crew on standby (except
TO)
- 2000 Requested Beam Permit
- 22:11 MCC tune beam through Hall A
- 23:02 Beam is ready. Move to LH2 15 cm and continue elastic scan
without sieve @ dp=-4%
- 23:40 Finish beam check. Start calibration run 7205
Run List
Elastics data, dp=-4% (3.194GeV)