• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT
    Make New Entry, Make Followup Entry

    User name adaq

    Log entry time 16:01:01 on October 17, 2010

    Entry number 335363

    keyword=Beam Time Accounting
    Hall A

    10/17/10 0800-1600
    Experiment #: DVCS
    Shift Leader: Juliette Mammei
    Shift Workers: TO: Shloka Chandavar

    08000900100011001200130014001500Total Time
    Acceptable Beam
    in Use
    0.160.960.930.470.000.000.000.002.52
    Beam Available
    but Not in Use
    0.800.020.040.530.910.940.520.664.42
    Beam Not Available
    or Unacceptable
    0.030.020.030.000.090.060.470.341.05
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    0.201.001.001.001.001.001.001.007.20
    Planned Config-
    uration Change
    0.800.000.000.000.000.000.000.000.80
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments:

    Data Entry by: Juliette Mammei