    keyword=Beam Time Accounting
    Hall A

    12/20/10 1600-2400
    Experiment #: nDVCS
    Shift Leader: B. Wojtsekhowski
    Shift Workers: Pan Kai, Rakitha BeminIwattha

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    0.800.910.950.960.920.880.980.987.38
    Beam Available
    but Not in Use
    0.200.070.050.020.060.110.020.020.53
    Beam Not Available
    or Unacceptable
    0.000.030.000.030.020.020.000.000.09
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.001.001.001.001.001.001.001.008.00
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.000.00
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments: DVCS LD2 production

    Data Entry by: bogdanw