We will be switching over to do some SRC commissioning between 3 and 4pm today, depending on when the last N->Delta run is over.
* Once the last N->Delta run is over, set up for SRC running:
- move
the RHRS to 14 degrees (keep the same momentum setting, 789 MeV)
- move
the LHRS to 54.4 degrees and change the momentum to 764.2 MeV/c
Here is the overall run plan for the next couple of days:
* SRC commissioning on deuterium until midnight Monday night
- Target warm-up starting at midnight to be warm by Tuesday morning
- Run on solid targets (thin carbon) until beam off (up to 5 uA)
* Beam off promptly at 7am Tuesday morning
* Target work to switch to 4He target
* pump down overnight (if all goes well)
* cool the target Wednesday (need to coordinate with Hall C cooldown)
* take beam as early as Wednesday swing
For reference, here is the SRC general run
plan.
Please don't hesitate to call the RC phone if you have any questions.