Target work will go on today. Shifts have been canceled through
Wednesday day (except for Wednesday TO which is on standby as of noon).
While the hall is open, DAQ work will be done, as well as some repairs to
the LHRS (including putting in the cerenkov) which are needed.
The HRS's need to switch polarity before we will be ready to take beam.
But the exact momenta and angles depend on when the target cool down will
happen.
If the Hall C target is not cooled down Wednesday (they are having vacuum
issues), and we are not ready to cool down Wednesday, we may have to wait
until Friday...
We are waiting on updates from the Hall C target group as well as the Hall A target group before we can try to finalize plans.