    keyword=Status update

    Status update: ------------------------------------ Detectors & DAQ:

    * Both HRS polarities have been flipped (L-negative, R-positive)---xiaohui, tech; * Left HRS GC has been plugged in, and DAQ is back---Jack, Zhihong * A couple of channals on the right HRS GC & pre/shower has been fixed---Zhihong * HAND trigger T7 is added---Or * Timing work on the trigger---Vince * BB & HAND DAQ test and prepare for cosmic data taking over night---Vince, Or, Igor * LHRS retiming issue investigation---Zhihong

    Target: * Target change completed and is pumping down, and the extra optics foils have been removed---Dave * Aiming to be ready tomorrow morning for the cool down. ----------------------------------------

    Reminder:

    target scattering chamber alarm was silenced, will need to be turned on once the target work is done.