    User name yez

    Log entry time 13:31:21 on March 10, 2011

    Entry number 351196

    keyword=R-HRS: re-arrangement of cables at Patch Panel (both up and downstairs) for PS#19R, Cer#5,#7

    I finished all my works in two HRSs and before I closed the doors, all
    detectors have been checked and function normally. (excpet S13L broad
    pedestal issue and double peaks of four Cer TDCs, which are not
    crucialfor the coming experiment.)
    
    Yestoday and today I did three cables' re-arrangement as following:
    
    1, PS19R: its cable from PMTs now connect to #15 of the slot for cerenkov
    at patch panel(up-PP-cer) upstairs. Correspondently,its BNCtoECL black
    cable connect to the #15 of cerenkov slot at patch panel
    downstairs(down-PP-cer), so the map in the ADC does not change.
    
    2, Cer#5,#7 cables from Cer's Amplifiers connect to to up-PP-cer #12,#14
    (#13 are bad, and #15 is for PS.19R), and as what PS19R does, the
    cables that go into ADC are connected to the corresponding channels at
    down-PP-cer. Hence, their maps also do not change.
    
    After those changes, all three counters' very broad pedestals are gone. 
    I put lables with reasons, my name and date on those cables that I moved,
    in case people might get confuse in the future. However, there are
    several bad channels in either Patch Panel upstairs or PP downstairs that
    are needed to be examed during shutdown:
                             PS#19R, Cer#5,Cer#7, S1#15,S1#16
    


    A copy of this log entry has been emailed to: doug, eip, rom,bogdanw,camsonne, vasulk,zhanxh,kalyan,solvigno