    User name adaq

    Log entry time 00:26:45 on March 17, 2011

    Entry number 352212

    keyword=Beam Time Accounting
    Hall A

    03/16/11 1600-2400
    Experiment #: e07006
    Shift Leader: Ole Hansen
    Shift Workers: Xin Qian (TO), Narbe Kalantarians (3rd)

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    0.960.850.780.900.280.490.950.826.02
    Beam Available
    but Not in Use
    0.030.110.210.050.690.490.030.161.79
    Beam Not Available
    or Unacceptable
    0.010.030.010.050.020.020.020.030.18
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.001.000.831.000.130.531.000.886.38
    Planned Config-
    uration Change
    0.000.000.170.000.000.000.000.000.17
    Unplanned
    Experiment Down
    0.000.000.000.000.870.470.000.121.45
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.120.12
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00
    Bigbite0.000.000.000.000.870.470.000.001.33

    Comments:

    Data Entry by: Ole Hansen