    keyword=Run plan for this week and beyond

    We have been advised to assume we cannot run in May due to 
    budgets and to optimize the April run time.
    
    Therefore, the next few weeks of run plan in block form is as follows.  
    The details and necessary adjustments are to be filled in by the RC 
    and spokespersons in the usual way.   
    
    -- Run SRC until the beam studies Wed Apr 13, or 1 pm,
                  whichever is earlier.
    
    -- DIS tour 3 to 5 pm Wed.  Lockup up 6 pm.
    
    -- Start e08009 (Fatiha).  Run until Fri 8 am.
    
    -- Fri 8 am pass change.  Start x > 2 experiment
    
    -- Mon Apr 18 at 8 am switch targets as planned (takes 3 days)
    
    -- Continue x > 2 until May 2 at 8 am.  Presumably beam off ?
    
    Now, a miracle could happen and we get great budgets.
    The schedule could change, but certainly not the part
    before Friday 8 am.
    
    