NEXT
Make New Entry,
Make Followup Entry
User name R. Michaels
Log entry time 08:52:33 on April 12, 2011
Entry number 355117
Followups:
keyword=Run plan for this week and beyond
We have been advised to assume we cannot run in May due to
budgets and to optimize the April run time.
Therefore, the next few weeks of run plan in block form is as follows.
The details and necessary adjustments are to be filled in by the RC
and spokespersons in the usual way.
-- Run SRC until the beam studies Wed Apr 13, or 1 pm,
whichever is earlier.
-- DIS tour 3 to 5 pm Wed. Lockup up 6 pm.
-- Start e08009 (Fatiha). Run until Fri 8 am.
-- Fri 8 am pass change. Start x > 2 experiment
-- Mon Apr 18 at 8 am switch targets as planned (takes 3 days)
-- Continue x > 2 until May 2 at 8 am. Presumably beam off ?
Now, a miracle could happen and we get great budgets.
The schedule could change, but certainly not the part
before Friday 8 am.
A copy of this log entry has been emailed to: hanretty,doug