User name A. Camsonne
Log entry time 14:51:12 on April 25, 2011
Entry number 357028
keyword=x >2 experiment status
Dear collaborators,
This week-end was quite productive, with a bit of interruption of beam
because of injector trips ( 5 hours ) and a bad CAMAC crate power supply
( about 2 or 3 hours ).
Other than that the experiment has been happily taking data with current
of 120 uA on He3, and 40 uA on Ca targets and dummy.
We just completed kinematics 5.2 and switched to Kinematic 5.0 this morning.
A spot move was done today since Hall A and Hall C have been drawing a
lot current from the gun.
.
Please consider taking a few additionnal shifts since owl shifts are
pretty thin and it seems running until May 13th is confirmed.
https://www1.jlab.org/mis/physics/shiftSchedule/index.cfm?experimentRunId=SRC
Best regards,
Alexandre Camsonne
Temporary Hall A run coordinator