Hall in controlled access (Left Q1 being fixed) at start of shift.
Beam back by 17:00, Began running ~17:15 with left arm only: Right dipole still ramping up.
19:35 Right arm is settled, start taking production with 2 arms.
Dipole still drifting a little, so have to check data to be sure it's stable enough.
19:30 ~30 min. of useless beam (constant trips). Come back ~20:00 with stable beam at 110 uA.
Continue data taking: 6400 events so far. (~1750/hr with both arms)
Runs:
3919 944 (L-arm)
3920 952
3923 504+481
3924 863+916
3925 838+900
3926 (in progress)