• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT
    Make New Entry, Make Followup Entry

    User name bogdanw

    Log entry time 16:04:12 on May12,2011

    Entry number 359025

    keyword=Shift summary

    SL: B.Wojtsekhowski
    TO: R.Lindgren
    3rd:Xinzhan Bai

    Summary

    SRC production data taking on 4He.
    Notable Events

    * 08:00 Shift starts with production data taking
    in progress on 20 cm 4He.

    Left Q2 tripped at about 3;30 during Run 4407
    Reset it remotely, then recycled it to 1600 with regulation off
    regulation on to reset current.

    Runlist

    * 4398 production, 4He, 1M, continued from owl shift
    * 4399 production, 4He, 1M,
    * 4400 1M,
    * 4401 production, 4He, 0.36M stop for Hall C Moller run
    * 4402 1M,
    * 4403 1M,
    * 4004 1M,
    * 4405 production, 4He, in progress
    * 4406 bad
    * 4407 production 4He .01M Q2 tripped
    * 4408 in progress