    User name R. Michaels

    Log entry time 09:04:34 on March26,2012

    Entry number 367295

    keyword=to-do list for Hall A to come back

    Kalyan (the run coordinator) is to coordinate.

    The goal is to get back up and running as soon as possible,
    but SAFELY, and with the approval of the 3-member committee
    (Bill Merz, Paul Brindza, Dave Mack).

    -- Install GFI on septum PS. Also on FZ magnet PS.
    responsible: Bill Merz's group

    -- Klixons on connectors
    responsible: Ed Folts and Jack Segal

    -- Alum block connections: use grease, torque to specs,
    develop written procedure to re-torque periodically
    responsible : Ed Folts and Jack Segal

    -- measure voltages at several places, especially weak coils
    responsible: Jack Segal

    -- high-pot to 400 V. Run a burn-in for several hours.
    responsible: Jack Segal

    -- finish the Lessons Learned document and get committee's
    approval to run
    responsible: Ed Folts with Javier Gomez

    -- checklist and lock up
    responsible: Ed Folts