Log entry time 09:04:34 on March26,2012
Entry number 367295
keyword=to-do list for Hall A to come back
Kalyan (the run coordinator) is to coordinate.
The goal is to get back up and running as soon as possible,
but SAFELY, and with the approval of the 3-member committee
(Bill Merz, Paul Brindza, Dave Mack).
-- Install GFI on septum PS. Also on FZ magnet PS.
responsible: Bill Merz's group
-- Klixons on connectors
responsible: Ed Folts and Jack Segal
-- Alum block connections: use grease, torque to specs,
develop written procedure to re-torque periodically
responsible : Ed Folts and Jack Segal
-- measure voltages at several places, especially weak coils
responsible: Jack Segal
-- high-pot to 400 V. Run a burn-in for several hours.
responsible: Jack Segal
-- finish the Lessons Learned document and get committee's
approval to run
responsible: Ed Folts with Javier Gomez
-- checklist and lock up
responsible: Ed Folts