NEXT
Make New Entry,
Make Followup Entry
User name jmaxwell
Log entry time 21:27:40 on April 13, 2012
Entry number 374068
keyword=Run Status, Plans
We are continuing with production data, although today has been a slog.
A beam trip due to a fuse on the chicane magnet's safety lamp cost about
half an hour, but returning good, centered beam after this trip was
problematic. In all these problems cost about 3 hours.
Production data continued in spite of high rate in the 3rd arm. This was
likely due to beam scraping the beam pipe somewhere, as the plots of the
slow raster at the target were clean.
Jixie and Chao worked for a couple hours after 18:00 to adjust the slow
raster size and beam position to avoid the beam pipe and keep the beam
off the target cup walls. Fortunately, this work was done while taking
production data, so it caused minimal delay. We are now running with the
beam offset to the right by 2mm to mostly avoid the pipe, while keeping
the raster open to a total 2cm to ensure the best possible polarization.
We will continue with production through the night. We should keep a
close eye on the target polarization, and scale the number of events for
each point to follow the polarization, as described in the run plan.
The target polarization is still above 30%, so we will plan for an anneal
early tomorrow morning. We will perform a tungsten calorimeter
calibration at the same time, and if there is time after that before the
anneal is done, we will have a quick access to allow a change to the
parasitic detectors.
Moving forward through next week, we will polarize the target only
positively to take advantage of the higher polarization that this
configuration offers for this time-strapped energy setting.
Day Summary:
0:00-10:30: Production
10:30-11:00: Access to fix chicane trip
11:00-14:00: Restore beam, centering
14:00-now: Production with slow raster and beam position study