We've had another smooth day with beautiful beam and steady target
polarization. There were essentially no delays, just production all day.
Production this weekend has exceeded expectations to the degree that we
are adding back in statistics at points that had been cut. We're
approaching points which should have lower rates, so we'll up the beam
current as needed.
If the beam current increases, another anneal may be needed tomorrow.
Hall C has continued to switch the half wave plate, so we haven't
requested it; we are continuing with positive polarization on both cups.
Day Summary:
0:00-23:00: Production