    User name L. Myers

    Log entry time 09:18:41 on March 14, 2014

    Entry number 386724

    keyword=RC summary of Acc meeting

    It was determined this morning at the accelerator meeting that beam will not be delivered to Hall A today. Accelerator will spend the weekend getting 3-pass beam up and stable before sending it to the hall. We will spend today cooling down the target. The new plan is to lock the hall at 8am on Monday (3/17) so that PSS certification can begin. Pulsed beam will then be delivered beginning at noon.

    Shift takers signed up for shifts on Friday, Saturday, Sunday or Monday should check their email for updated schedules.