    User name Kalyan

    Log entry time 12:49:59 on March 21, 2014

    Entry number 387113

    Followups:

    keyword=RC summary 3/21

    The Hall was in controlled access this morning to check some remaining
    issues. It will lock up around 1 pm. MCC will continue to optimize their
    optics and do some stability studies for rest of the Swing and Owl shifts
    tonight. We will need shift crew in the counting as planned. 
    
    We plan to use a solid target during the day shift tomorrow (Sat) and
    being checking out HRS detectors. These checkouts will continue for rest
    of the weekend. There is also a plan to go through Compton chicane on
    Sunday (Day). We will have regular shifts starting day shift on Saturday
    (22nd).
    