    User name V. Sulkosky

    Log entry time 23:14:15 on March 22, 2014

    Entry number 387299

    keyword=Run Plan Swing + Owl March 22-23

    Updated run plan from the RC, Kalyan.
    
    During the rest of Swing and all of Owl shift, the plan is to take data on
    the carbon target with a maximum current of 10 uA (pulsed beam).  The goal
    is to acquire either 100,000 events or 1 hour of data for each of the
    following triggers T1, T2, T3, T4, T5, and T6, one trigger at a time for
    the left HRS.  The right HRS (with Q1 being off) does not see any real
    rate from the target.  Hence, we will take right HRS data with only T1
    for perhaps 2 hours at a time, while taking the hourly runs for the left HRS.
    
    At 7:45, the shift leader should request for the ARM to come so that
    Heidi can enter the Hall when she arrives at 8:00 am to move the right
    HRS from 33 degrees to 15 degrees.
    


    A copy of this log entry has been emailed to: baraks,jroche,kalyan