• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT
    Make New Entry, Make Followup Entry

    User name V. Sulkosky

    Log entry time 00:06:27 on March 23, 2014

    Entry number 387307

    keyword=Swing Shift Summary

    Swing Shift Workers:
    
    V. Sulkosky (SL)
    K. Aniol (TO)
    N. Israel (3rd)
    
    16:00 Start of Swing Shift
    17:05 Talked with MCC, no estimate on beam delivery.
    18:30 Talked with MCC, progress is being made, but no time estimate yet.
    19:02 The issue with 2L26 fast valve is solved!  MCC should be ready in
    10-15 minutes to start with the beam.
    19:23 Moved target to BeO and waiting for 5 uA of tune beam.
    20:00 Moved target to Carbon and ready to take data at 5 uA pulsed beam.
    20:36 MCC is having an issue with a cavity in the SL.  Current has been
    off for some time.
    20:48 Beam is back.
    21:13 Ask for 10 uA of pulsed beam.
    21:54 Beam off due to a problem with cavity 1L04.
    22:15 RF on-call coming into look at a fault with 1L04.
    23:00 Beam is back at 10 uA.
    24:00 End Shift with beam on carbon.