NEXT
Make New Entry,
Make Followup Entry
User name V. Sulkosky
Log entry time 18:07:06 on March 23, 2014
Entry number 387437
keyword=Swing Shift Run Summary
Swing Shift Workers:
V. Sulkosky (SL)
K. Aniol (TO)
N. Israel (3rd)
16:00 Start of Swing Shift
16:25 Talked with MCC, no estimate on beam delivery.
16:40 Moved the right HRS sieve-slit OUT to 6 msr.
16:50 Started the ALH on hacweb7.
16:50 Turned right dipole regulation ON.
17:15 MCC called and said the prognosis is not good. Beam is not likely
until tomorrow.
17:30 RC, Kalyan, calls canceling the remainder of swing shift today and
owl shift tomorrow morning.
17:32 Target moved from Carbon to Empty.
17:35 MCC called about taking us to controlled access. RC agrees.
17:45 Noticed left dipole tripped. Reset and brought it back up to 340 Amps.
A copy of this log entry has been emailed to: kalyan