User name E. Christy
Log entry time 00:26:45 on March30,2014
Entry number 388080
keyword=Swing shift summary
SL: E. Christy
TO: T. Gautam
RC: C. Munoz
================
17:00 - 18:30 no beam
16:30 - 20:00 beam centering
Found beam in reasonable position on BeO, but HRSL rates on empty target indicated
that the beam was hitting the target frame. Eventually eliminated the rate after moving the beam +4mm vertically. Spent most of the rest of the shift trying to refine the beam positioning using the carbon hole target.
Found the beam to be centered on the carbon hole for bpm A positions of (0mm, 3mm).