Log entry time 00:18:52 on September 27,1998
Entry number 1570
keyword=Shift summary
16:00 Start Moller test
Put reference cell in in order to shake down shower counters
Pressure of Nitrogen in cell is 1.1 atm
19:30 Control access to look at heater-it looks fine
20:00 Beam back for moller measurement
20:20 Mark Stevens is allowed in the hall to fix air flow for target.
He repaired the air compressor
21:15 Spin dance is cancelled since Moller group does not understand
asymmetry of beam in the two spin states. They suspect a problem
with the laser our Pockels cell at the source.
21:20 Mott measurement is done.
22:00 Moller group decides to go ahead with the spin dance anyway
23:30 4 points of the spin dance have been completed
23:40 Wien filter has been adjusted to optimize polarization to Hall C
since Hall A has not started production running yet.
00:00 Reference cell has been taken out and an access is being made
to asses the reference cell leaks.
Note: during the evening CODA was crashing every other run
not sure why.