    Hall A

    11/21/1998 1600-2400
    Experiment #: E94-010
    Shift Leader: Deur A.
    Shift Workers: R. DiSalvo, M. Finn, H. Ueno

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    55 50 1 1 30 1 40 1 6.91666666666667
    Beam Available
    but Not in Use
    5 10 0 0 30 0 20 0 1.08333333333333
    Beam Not Available
    or Unacceptable
    0 0 0 0 0 0 0 0 0
    Accelerator Con-
    figuration Chage
    0 0 0 0 0 0 0 0 0
    Experiment
    Ready
    55 50 1 1 30 1 40 1 6.91666666666667
    Planned Config-
    uration Change
    5 10 0 0 30 0 20 0 1.08333333333333
    Unplanned
    Experiment Down
    0 0 0 0 0 0 0 00
    Hall not
    ready reasons
    Target 5 0 0 0 0 0 0 0 0.0833333333333333
    HRSe 0 0 0 0 0 0 0 0 0
    HRSh 0 0 0 0 30 0 20 0 0.833333333333333
    Data Acq 0 0 0 0 0 0 0 0 0
    Other 0 0 0 0 0 0 0 0 0

    Comments: 16:55 NMR measurement. Target polarization 35 % switch target configuration from // to |_ (Ep=689 MeV) 19:45 Changed Magnet setting to Ep=587 MeV did an NMR:34.5 %. Back to // 22:45 go to |_ + NMR :35 %

    Data Entry by: A Deur