• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT

    User name adaq

    Log entry time 15:56:16 on November 28, 1998

    Entry number 6858

    keyword=Beam Time Accounting
    Hall A

    11/28/1998 0800-1600
    Experiment #: E94-010
    Shift Leader: incerti
    Shift Workers: E. Lakuriqi, F. Xiong, F. Sabatie

    08000900100011001200130014001500Total Time
    Acceptable Beam
    in Use
    0 0 0 0 0 0 0 0 0
    Beam Available
    but Not in Use
    0 0 0 0 0 0 0 0 0
    Beam Not Available
    or Unacceptable
    1 1 1 1 1 1 1 1 8
    Accelerator Con-
    figuration Chage
    0 0 0 0 0 0 0 0 0
    Experiment
    Ready
    0 0 0 0 0 0 0 0 0
    Planned Config-
    uration Change
    1 1 1 1 1 1 1 1 8
    Unplanned
    Experiment Down
    0 0 0 0 0 0 0 00
    Hall not
    ready reasons
    Target 0 0 0 0 0 0 0 0 0
    HRSe 0 0 0 0 0 0 0 0 0
    HRSh 0 0 0 0 0 0 0 0 0
    Data Acq 0 0 0 0 0 0 0 0 0
    Other 0 0 0 0 0 0 0 0 0

    Comments: - spin-up - NMR every 2 h - stand-by shift

    Data Entry by: incerti