    16:00 taking radiator out + 1H data

    16:45 shut down for system checks

    17:30 beam back from system checks

    19:37 starting with run 2542, take gamma + p data, as have about .55 C of
    .64 C desired for radiator out.

    23:00 MCC warns us beam will be off for a few minutes for tuning to Hall C.

    23:20 beam back, take more data