    Data taking at recoil 400 MeV/c til 10 am.
    Ed Foldts called, to change hadron angle to 92.759 deg, recoil 500 MeV
    Change finished at 10:40, but Hall B requires tuning time.
    at 11:40 we get about 10 min beam and do run 2630
    Hall B continues to tune, we continue to iddle.
    15:00 restart of operation, do Al foils 4 cm, and HARP scan
    15:20 start taking data with 100 microA, recoil 500 MeV/c