Shutdown activities - PREX


updated Jan 4, 1:00 pm


  Remove PVDIS crates, Cherenkov, LG, S1.
                (Jack, Ramesh, students.)

  Moller Installation

     -- high-field magnet (Ed, Javier, Sasha, Roman)
     -- SU scint  (Sasha, Dustin, Zafar)
     -- DAQ shakedown (Roman, Zafar, Brad, Mindy)

  Compton Work

     -- Install cavity (Sirish, Abdurahim, Mark)
           [Sirish has a very detailed plan here]
     -- Try new Trig. Super. mode (Bob, Alex)
     -- Tests at 240 Hz flip rate (Bob, Alex, Megan)
     -- Survey beamline, fix kink (Megan)
     
  Install PREX detectors (Jack, KK, Dustin)

  Install Collimator (Ed and crew)

     -- follow alignment plan 

  Install Septum  (Ed and crew)

     -- prior field mapping (John LeRose, Mindy)

  Install Lead Target (Meekins)

     -- pre-assembly (Bob, Phil Adderly)

  Cavities (John Musson, Zafar, Xiaoyan)

     -- fix default dynamic range (1-2 V offset)
     -- prepare for 10 nA ops -- amplifiers

  Polarized Source Setup (Kent, Rupesh)
  
  New GEM Detector for Qsq 
  (Ole, Nilanga, Alex, Evaristo, Guido, Seamus)

  RSAD, ESAD, COO (Bob)

     -- get RSAD info to Pavel (Bob)

  Organize the schedules of

     -- Run Coordinators (Bob, KK, Kent)
     -- WAC (Mark)
     -- Shift workers (Mark)

  Parity DAQ (Luis, Bob)

     -- Install more 18-bit ADCs 
     -- 240 Hz ET test
     -- Oversampling and synch tests

  Prepare Online and Offline Analysis 

     -- Panguin, prompt (Mark, Kent, Rupesh, Kai)
     -- HRS/Podd analysis (Dustin, Bob)

  Develop PREX Run Plan (KK, Bob, Paul, Kent)